Kuala Lumpur · Jalan Cochrane / Maluri
Sunway Cochrane
Sunway Cochrane is a two-tower serviced-apartment development along Jalan Cochrane. Its 1,296 residences sit above a mixed urban setting with retail at the base. The developer’s plans combine adaptable layouts with smart-home features and landscaped communal spaces. The proposed connection to Cochrane MRT is central to its transit-oriented concept, while the two towers and their shared podium form one distinct project, separate from Sunway Velocity 3.
01 · The project
Key project facts
- Developer
- Sunway Cochrane Sdn Bhd / Sunway Property
- Location
- Kuala Lumpur
- Property types
- Serviced apartments with adaptable layouts
- Storeys
- TEDUH registers two residential components of 54 and 55 storeys
- Residences
- 1,296; Tower A: 641, Tower B: 655
- Land area
- Approx. 21,850 m²
- Unit sizes
- Approx. 60–93 m²
- Announced completion
- Developer target: October 2029; TEDUH first-contract timetable: 19 November 2029
Planned amenities
- Pool terrace
- Gym
- Children’s playground
- Landscaped communal spaces
- Sky dining spaces
From the project presentation; not confirmation that facilities are already usable.
02 · The location
Location & surroundings
Sunway Cochrane
Kuala Lumpur
Loading sends connection data to OpenFreeMap.The official project information describes a 60-metre link bridge to Cochrane MRT and nearby IKEA Cheras, MyTOWN and Sunway Velocity. Completion of individual connections is not independently confirmed.
03 · Development
Progress & timeline
Official TEDUH record 8824-5 reports 20% for each of two residential components, covering 641 and 655 homes. No CCC or vacant-possession date is shown. The public response does not expose the component reporting month, so these readings are attributed to the register retrieved on 17 October 2026. The developer’s site photograph separately shows earthworks but is undated. October 2029 is the advertised target; the extended first-contract timetable ends on 19 November 2029.
Developer target: October 2029; TEDUH first-contract timetable: 19 November 2029Construction status reflects the cited information at the time of review. Individual buildings, amenities and handovers may follow different schedules.