Valley is a completed residential mixed-use development in Amsterdam’s Zuidas district, developed by EDGE and designed by MVRDV. Three towers rise approximately 67, 81 and 100 metres around stone terraces and planting designed with Piet Oudolf. MVRDV and the residential operator describe 200 apartments. Offices, restaurants and public spaces complement the homes, including the elevated valley and Grotto atrium. The approximately 75,000 m² figure describes gross floor area across the development. First residents arrived in late 2021; the full public opening followed in September 2022.

Completed

Editorial research
Reviewed: October 17, 2026

01 · The project

Key project facts

Developer
EDGE
Location
Amsterdam
Property types
Apartments within a mixed-use development with offices, restaurants and public spaces
Storeys
Not yet verified
Residences
200 apartments, according to MVRDV and the residential operator
Land area
Not yet verified
Unit sizes
Approximately 55 m² to over 400 m² (residential operator)
Announced completion
First occupation late 2021; full public opening September 2022

Planned amenities

  • Planted terraces and landscaped spaces designed with Piet Oudolf
  • Public elevated valley on the fourth and fifth floors
  • Public Grotto atrium and external stone stairways

From the project presentation; not confirmation that facilities are already usable.

02 · The location

Location & surroundings

Valley

Amsterdam

Loading sends connection data to OpenFreeMap.
Verified building point. Open in OpenStreetMap

Beethovenstraat 301–781, 1083 HK Amsterdam, in the Zuidas district near Amsterdam Zuid station. The map marks the named Valley building footprint; it is an approximate project location, not a particular apartment entrance.

03 · Development

Progress & timeline

Completed

Completed. MVRDV records the arrival of the first residents and businesses in late 2021 and the full opening in September 2022. EDGE’s current portfolio separately lists Q1 2023 as completion. These are different reported milestones; no single apartment handover date or current availability is inferred.

First occupation late 2021; full public opening September 2022

Construction status reflects the cited information at the time of review. Individual buildings, amenities and handovers may follow different schedules.