Queensland · Greenbank / Teviot Road
Everleigh by Mirvac
Everleigh is a staged residential community in Greenbank, Logan City, south of Brisbane. Mirvac’s FY26 register lists 3,296 indicative residential lots across approximately 4,810,000 m². The register separates 929 lots in completed stages, 806 in released stages and 1,561 in future stages. Those are development-stage lot counts rather than counts of completed houses. Established community features include parks, an AFL precinct and Everleigh State School. Conservation open space and future recreational areas form part of the wider plan. This profile covers the community as a whole, with occupied areas and ongoing subdivision work; it does not represent a single house release or a uniformly unfinished site.
01 · The project
Key project facts
- Developer
- Mirvac
- Location
- Logan City
- Property types
- Residential land lots and house-and-land community
- Storeys
- Not yet verified
- Residences
- 3,296 indicative residential lots in the FY26 register
- Land area
- Approximately 4,810,000 m² across the wider community
- Unit sizes
- Not yet verified
- Announced completion
- Staged development; individual lot and home completion dates vary
Planned amenities
- Community parks and events lawn
- Sports park and AFL precinct
- Conservation open space
From the project presentation; not confirmation that facilities are already usable.
02 · The location
Location & surroundings
Everleigh by Mirvac
Logan City
Loading sends connection data to OpenFreeMap.Greenbank, Logan City, Queensland, around Teviot Road. The named OSM Everleigh Estate area matches Mirvac’s Greenbank location and surrounding estate landmarks. Approximate marker within the wider community, not its full boundary, a particular release or the sales-office pin.
03 · Development
Progress & timeline
Mirvac’s FY26 register, as at 30 June 2026, lists 929 lots in completed stages, 806 in released stages and 1,561 in future stages. Released-stage construction progress is 89% by cost, including subdivision and excluding land acquisition; this is not the share of houses completed or a percentage for the whole estate. The official project-update page also lists a September 2026 construction update.
Staged development; individual lot and home completion dates varyConstruction status reflects the cited information at the time of review. Individual buildings, amenities and handovers may follow different schedules.